About Flow Statuses

Each flow has two tabs: "In Progress" and "Completed." Flows listed under "In Progress" will automatically move to the "Completed" tab once all tasks within the flow are finished.38-FlowComplete-01


How to Force a Flow to Complete

In the flow list view, click on the "..." icon next to the flow you wish to complete. From the dropdown menu that appears, select "Complete."39-FlowComplete-02


A final confirmation alert will be displayed. To proceed with completing the flow, simply click "Complete."40-FlowComplete-03


The corresponding flow will be moved to the "Completed" tab.